Client:  Echelon Data Centres
City:  Dublin, Ireland
Role:  Project Manager
Sector:  Mission Critical
Status:  Pre-Construction
Value:  €450 million

FTSQUARED have been retained as Project Manager on the development of two large scale data centre campuses in Dublin: Clondalkin and Avoca.

Planning is in place for Clondalkin which is a 44,323m2  data centre. Work on phase 1 has commenced with the development of 40 MW of capacity which will be powered by the national grid. Full planning permission is in place for an 84MW on-site power station. Initial occupation is due to be in Q3 2020.

Planning permission is imminent for 3 data centre buildings, a sub-station and ancillaries totalling over 45,000m². Phase 1 will deliver up to 100MW of capacity on a 30-acre sub-site and initial occupation is due in Q1 2020.

 

 