Client:  Echelon Data Centres
Location:  Arklow, Ireland
Role:  Project Manager
Sector:  Mission Critical
Status:  In Planning
Value:  €450 million

Planning permission in place for 3 data centre buildings, sub-station and ancillaries totalling over 500,000sqf.

DUB – 20 will sit on a 200-acre site strategically located in the southeast of Ireland, some 60 minutes drive from Dublin and adjacent to the national motorway network

Phase 1 will deliver up to 100MW of capacity on a 30-acre sub-site

Initial occupancy from Q1 2021.